Project Description

 
The project will replace water mains along Randolph St from Concordia Ln to Wilmington Dr.  Project will improve fire flow and provide additional flow for the Villages of Provence development project.  

Project Location


Randolph Street from Concordia Ln to Wilmington Dr. 

Contact Information


Nick Galla
Project Manager
636-949-3237

Current Project Activities

 
  • Preliminary Plan Approval completed April 2016
  • Field survey completed March 2016
  • Project Charter was approved September 2015

Project Timeline

Randolph timeline

Project Progress

Randolph progress

Project Budget

randolph budget