Cole Creek Flood Reduction Project - Elm to Droste

Project Description


Complete improvements to reduce flooding along Cole Creek.  Design of the project has been contracted to M3 Engineering Group, P.C. The design is anticipated to be completed in December 2017 with construction beginning in summer 2018. 

Project Location


BSNF Railroad Crossing to up stream of Shelburne Drive

Contact Information


John Reeves
Project Manager
636-949-3237

Current

Project Activities

  • Design of the project has been contracted to M3 Engineering
  • Design is anticipated to be complete in December 2017
  • Construction is anticipate to being in summer 2018
  • Engineering team is currently gathering on site data such as photographs, surveys and soil samples


Project Timeline

cole creek timeline

Project Progress

cole creek progress