Current Project Activities
  • The City has completed design plans and specifications a for the new water well
  • Bids were opened March 2, 2016
  • Construction of the well began in April 2016
  • The contractor has finished drilling the well and has installed a new 12” raw water line and valve vault
  • The contractor is constructing the platform

Project Timeline