Exposed Sanitary Sewer Pipes in Creek Bank

Project Description
During a creek inspection, City staff identified two locations where the creek erosion has exposed the sanitary sewer main. The pipe is not encased and is in danger of being damaged by floating debris during a storm event. The Graystone Dr. location runs parallel to the Cole Creek and could be moved back into the creek bank with stabilizing the creek bank to prevent further erosion. The Wimbly Pl. location is a creek crossing where the main channel has cut below the pipe. The pipe should be encased and incorporated into a new grade control structure. The project is intended to protect/move the exposed sanitary sewer mains that are located within a creek.

Project Location
Along a portion of Graystone Drive and Wimbly Place.

Contact Information
 Rodney Edwards
Project Manager
636.949.3237

Current Project Activities
  • Construction began in November 2015.
  • McNair North and South were completed on December 15, 2015 with only punch list items remaining.
  • 8 Wimbly was completed on January 8, 2016 with only sodding and punch list items remaining.
  • Graystone Drive will be ready for plantings the week of February 8 - February 12, 2016.

Project Timeline

exposed timeline

Project Progress

exposed progress

Project Budget

exposed budget
This project was made possible through Capital funds.