Lindenwood Avenue Culvert Replacement

Project Description


The Lindenwood Avenue Culvert was identified as a high priority replacement after an inspection in 2013. The project will replace a deteriorated 6' diameter Corrugated Metal Pipe (CMP) with with a concrete box culvert.
.

Project Location


Located on Lindenwood Ave, over Boschert Creek between Jolruns Pl. and Gallagher Ave.
Project Map

Contact Information


Marty Aubuchon
Project Manager
636-949-3237

Current Project Activities


  • In construction phase
  • Lindenwood Ave will be closed between Jolruns & Gallaher Ave. beginning September 6, 2016
  • Traffic will be routed to the north on Pine Street and signs will be placed on Park Ave & Gallaher Ave to advice motorists of the detour
  • Concrete box culvert was installed in September
  • Crews began installing streambank protection in September
  •  Permits have been obtained from Missouri Department of Natural Resources and Corps of Engineers
  • Utility coordination is complete
  • Final Plans, Specifications, and Estimates are complete

Project Timeline

lindenwood timeline

Project Progress

lindenwood progress

Project Budget

Lindenwood Avenue Project Budget
This project made possible through Capital funds.