94 Water Tower

Project Description


The City of St. Charles' Water Master Plan indicated insufficient elevated water storage. A new water tower was recommended to provide sufficient capacity to serve existing and future development. This project will design and construct a new 2.0 million gallon water tower along Highway 94.


Project Location


1805 South Old Highway 94
Project Map

Contact Information


Coralie Steuber
Project Manager
 636-949-3237

Current

Project Activities

  • Contractor: Caldwell Tanks, Inc
  • The site survey for this project has been completed
  • Crews have demoed the site by removing concrete within the footprint of the new tank and a small block building at the back side of the site
  • The contractor crushed some of the demoed concrete to reuse on the site
  • The contractor has installed temporary fencing around the site as a safety barrier and to protect their equipment and supplies throughout the construction process
  • The foundation crew mobilized on April 19, 2016 and began installing auger cast piles
  • The auger cast pile installation was completed on April 25, 2016
  • The Contractor poured the concrete pile cap and work surface on April 28, 2016
  • The pedestal wall was completed the first week of August
  • The concrete dome was complete in early August
  • Steel work began in August
  • Painting crew is expected to arrive in mid-October

 

Project Timeline

94 water tower timeline

Project Progress

94 water tower progress

Project Budget

Hwy 94 Water Tower Project Budget
This project made possible through Water funds and bonds.

Project Risks

94 Water Tower Risks
If you have any questions regarding the project risks, please contact the project manager at the Public Works office, 636-949-3237.